The cost of taking shape.

Public documents report major spending categories, but do not provide a complete vendor-level general ledger. Reported spending and engineer estimates answer different questions.

Site updated

Sources added through Nov 1, 2026; each fact retains its own date.

Glades County records checked through . Individual sources and historical collection batches retain their own dates.

Reported spent↗

≈$35M

Land development#

Developer-reported Sources (1) ↗

Source record

Evidence behind the record

Supports

As of October 2025, the developer reported approximately $34.59 million to $35 million in land-development costs.

  1. Lakefront Estates CDD Limited Offering Memorandum / Official Statement

    Document date
    Dec 11, 2025
    Source type
    Official offering document
    Confidence
    Primary source
Reported spent↗

≈$18M

Vertical construction#

Developer-reported Sources (1) ↗

Source record

Evidence behind the record

Supports

As of October 2025, the developer reported approximately $18 million in vertical construction spending.

  1. Lakefront Estates CDD Limited Offering Memorandum / Official Statement

    Document date
    Dec 11, 2025
    Source type
    Official offering document
    Confidence
    Primary source
Reported spent↗

≈$3.5M

General conditions#

Developer-reported Sources (1) ↗

Source record

Evidence behind the record

Supports

As of October 2025, the developer reported approximately $3.5 million in general conditions.

  1. Lakefront Estates CDD Limited Offering Memorandum / Official Statement

    Document date
    Dec 11, 2025
    Source type
    Official offering document
    Confidence
    Primary source
Reported spent↗

≈$33M

A&E, consulting, marketing & financing#

Combined category. Marketing cannot be isolated from this figure.

Developer-reported Sources (1) ↗

Source record

Evidence behind the record

Supports

As of October 2025, the developer reported approximately $33 million in a combined category of architecture and engineering, consulting, marketing, and financing costs. Marketing is not isolated inside this category.

  1. Lakefront Estates CDD Limited Offering Memorandum / Official Statement

    Document date
    Dec 11, 2025
    Source type
    Official offering document
    Confidence
    Primary source

≈$89.5M Derived sum of the reported categories · Oct 1, 2025

These categories may overlap and are not an audited capital stack or proof of all project spending.

Derived Sources (1) ↗

Source record

Evidence behind the record

Supports

Arithmetic sum of the four reported categories: About $35 million + About $18 million + About $3.5 million + About $33 million combined. Completeness and non-overlap are not established.

  1. Lakefront Estates CDD Limited Offering Memorandum / Official Statement

    Document date
    Dec 11, 2025
    Source type
    Official offering document
    Confidence
    Primary source

Land-acquisition figures from two sources#

$8,906,250 deed consideration

Dated observation

The November 9, 2021 warranty deed carries a handwritten consideration figure of $8,906,250 and documentary stamps of $62,344.10.

Public record As of Nov 9, 2021

PDF page 1 also has the standard printed $10-and-other-consideration wording. The later offering document reports about $13.9 million acquisition cost; the reviewed records do not explain the difference. This is the original project-land acquisition, not an individual home closing.

Public record Sources (1) ↗

Source record

Evidence behind the record

Supports

The November 9, 2021 warranty deed carries a handwritten consideration figure of $8,906,250 and documentary stamps of $62,344.10. PDF page 1 also has the standard printed $10-and-other-consideration wording. The later offering document reports about $13.9 million acquisition cost; the reviewed records do not explain the difference. This is the original project-land acquisition, not an individual home closing.

  1. Warranty deed: Glenn C. Harvey to the developer — instrument 202122003525

    Recording date
    Nov 16, 2021
    Source type
    Public record
    Confidence
    Primary source
    Location
    Instrument 202122003525; Official Records book/page 376/333; 4 PDF pages

    Read page-cited instrument summary →

    Recorded 2021-11-16. Document dated 2021-11-09. Retrieve by instrument number from the county search portal. Source-page summaries appear in the instrument register. Downloaded October 7, 2026; county verification notice through September 30, 2026.

    Open original source ↗ Opens a leaving notice in a new tab.

About $13.9 million

Reported spent

December 2025 CDD documentation states the approximately 525-acre land was acquired for about $13.9 million.

Official offering document As of Dec 11, 2025

About $3.5 million was attributed to Assessment Area One. The 2021 deed separately shows $8,906,250 in handwritten consideration. The relationship between these differently reported amounts is not explained by the reviewed records.

CDD document Sources (2) ↗

Source record

Evidence behind the record

Supports

December 2025 CDD documentation states the approximately 525-acre land was acquired for about $13.9 million. About $3.5 million was attributed to Assessment Area One. The 2021 deed separately shows $8,906,250 in handwritten consideration. The relationship between these differently reported amounts is not explained by the reviewed records.

  1. Lakefront Estates CDD Limited Offering Memorandum / Official Statement

    Document date
    Dec 11, 2025
    Source type
    Official offering document
    Confidence
    Primary source
  2. Warranty deed: Glenn C. Harvey to the developer — instrument 202122003525

    Recording date
    Nov 16, 2021
    Source type
    Public record
    Confidence
    Primary source
    Location
    Instrument 202122003525; Official Records book/page 376/333; 4 PDF pages

    Read page-cited instrument summary →

    Recorded 2021-11-16. Document dated 2021-11-09. Retrieve by instrument number from the county search portal. Source-page summaries appear in the instrument register. Downloaded October 7, 2026; county verification notice through September 30, 2026.

    Open original source ↗ Opens a leaving notice in a new tab.

Phase 1 improvements recorded in February 2026#

$35,138,068.25 Phase 1 estimate

Estimated

The Phase 1 cost cover recorded February 20, 2026 totals projected improvements at $35,138,068.25.

Public record As of Feb 20, 2026

PDF page 43: $28,063,135 civil improvements, $3,301,211.25 offsite watermain and $3,773,722 wastewater treatment. Different scope and date from the Assessment Area One estimate.

Public record Sources (1) ↗

Source record

Evidence behind the record

Supports

The Phase 1 cost cover recorded February 20, 2026 totals projected improvements at $35,138,068.25. PDF page 43: $28,063,135 civil improvements, $3,301,211.25 offsite watermain and $3,773,722 wastewater treatment. Different scope and date from the Assessment Area One estimate.

  1. Phase 1 construction assurances and performance bonds — instrument 202622000484

    Recording date
    Feb 20, 2026
    Source type
    Public record
    Confidence
    Primary source
    Location
    Instrument 202622000484; Official Records book/page 423/607; 55 PDF pages

    Read page-cited instrument summary →

    Recorded 2026-02-20. Document dated 2026-02-13. Retrieve by instrument number from the county search portal. Source-page summaries appear in the instrument register. Downloaded October 7, 2026; county verification notice through September 30, 2026.

    Open original source ↗ Opens a leaving notice in a new tab.

$43,922,685.32 printed assurance estimate

Estimated

The same cover prints $43,922,685.32 as the projected cost including 25%.

Public record As of Feb 20, 2026

PDF page 43. Multiplying the stated $35,138,068.25 base by 1.25 yields $43,922,585.31 after rounding, a $100.01 difference. The printed number is retained as a source figure; it differs from the actual $44,817,636 bond principal total.

Public record Sources (1) ↗

Source record

Evidence behind the record

Supports

The same cover prints $43,922,685.32 as the projected cost including 25%. PDF page 43. Multiplying the stated $35,138,068.25 base by 1.25 yields $43,922,585.31 after rounding, a $100.01 difference. The printed number is retained as a source figure; it differs from the actual $44,817,636 bond principal total.

  1. Phase 1 construction assurances and performance bonds — instrument 202622000484

    Recording date
    Feb 20, 2026
    Source type
    Public record
    Confidence
    Primary source
    Location
    Instrument 202622000484; Official Records book/page 423/607; 55 PDF pages

    Read page-cited instrument summary →

    Recorded 2026-02-20. Document dated 2026-02-13. Retrieve by instrument number from the county search portal. Source-page summaries appear in the instrument register. Downloaded October 7, 2026; county verification notice through September 30, 2026.

    Open original source ↗ Opens a leaving notice in a new tab.

$44,817,636 performance bonds

Dated observation

The February 13, 2026 county-attorney affidavit identifies two developer performance bonds totaling $44,817,636: $20 million dated April 11, 2025 and $24,817,636 dated January 29, 2026.

Public record As of Feb 13, 2026

PDF pages 1, 52 and 54. The developer is principal, Great Midwest Insurance Company surety, and Glades County obligee. These are improvement assurances, not CDD bond proceeds or construction spending.

Public record Sources (1) ↗

Source record

Evidence behind the record

Supports

The February 13, 2026 county-attorney affidavit identifies two developer performance bonds totaling $44,817,636: $20 million dated April 11, 2025 and $24,817,636 dated January 29, 2026. PDF pages 1, 52 and 54. The developer is principal, Great Midwest Insurance Company surety, and Glades County obligee. These are improvement assurances, not CDD bond proceeds or construction spending.

  1. Phase 1 construction assurances and performance bonds — instrument 202622000484

    Recording date
    Feb 20, 2026
    Source type
    Public record
    Confidence
    Primary source
    Location
    Instrument 202622000484; Official Records book/page 423/607; 55 PDF pages

    Read page-cited instrument summary →

    Recorded 2026-02-20. Document dated 2026-02-13. Retrieve by instrument number from the county search portal. Source-page summaries appear in the instrument register. Downloaded October 7, 2026; county verification notice through September 30, 2026.

    Open original source ↗ Opens a leaving notice in a new tab.

The affidavit and engineering exhibits contain projected costs and performance assurances for all of Phase 1. These have different dates and scopes from the spending and Assessment Area One tables below; they are not added together.

Developer-reported spending as of October 2025#

Figures reported in the December 2025 offering document
CategoryReported amountStatus
Land development $34.59 million to about $35 million
Developer-reported Sources (1) ↗

Source record

Evidence behind the record

Supports

Land development: $34.59 million to about $35 million. Reported October 2025.

  1. Lakefront Estates CDD Limited Offering Memorandum / Official Statement

    Document date
    Dec 11, 2025
    Source type
    Official offering document
    Confidence
    Primary source
Vertical construction About $18 million
Developer-reported Sources (1) ↗

Source record

Evidence behind the record

Supports

Vertical construction: About $18 million. Reported October 2025.

  1. Lakefront Estates CDD Limited Offering Memorandum / Official Statement

    Document date
    Dec 11, 2025
    Source type
    Official offering document
    Confidence
    Primary source
General conditions About $3.5 million
Developer-reported Sources (1) ↗

Source record

Evidence behind the record

Supports

General conditions: About $3.5 million. Reported October 2025.

  1. Lakefront Estates CDD Limited Offering Memorandum / Official Statement

    Document date
    Dec 11, 2025
    Source type
    Official offering document
    Confidence
    Primary source
Architecture and engineering, consulting, marketing, and financing About $33 million combined
Developer-reported Sources (1) ↗

Source record

Evidence behind the record

Supports

Architecture and engineering, consulting, marketing, and financing: About $33 million combined. Reported October 2025.

  1. Lakefront Estates CDD Limited Offering Memorandum / Official Statement

    Document date
    Dec 11, 2025
    Source type
    Official offering document
    Confidence
    Primary source

These categories are roughly $90 million if added, but the source is not treated here as proof that the list is exhaustive or non-overlapping. No total is labeled as all project spending.

About $33 million combined

Reported spent

As of October 2025, the developer reported approximately $33 million in a combined category of architecture and engineering, consulting, marketing, and financing costs.

Developer-reported As of Oct 1, 2025

Marketing is not isolated inside this category.

Developer-reported Sources (1) ↗

Source record

Evidence behind the record

Supports

As of October 2025, the developer reported approximately $33 million in a combined category of architecture and engineering, consulting, marketing, and financing costs. Marketing is not isolated inside this category.

  1. Lakefront Estates CDD Limited Offering Memorandum / Official Statement

    Document date
    Dec 11, 2025
    Source type
    Official offering document
    Confidence
    Primary source

February 2024 capital-improvement estimates#

Estimate, not money spent
CategoryEstimated cost
Land acquisition $13,900,000
Wetlands basins $1,700,000
Earthwork $18,357,220
Roadway construction $30,329,955
Entrance features $408,534
Water supply facilities $24,607,774
Sewer facilities $12,215,795
Stormwater facilities $2,279,455
Electrical $1,600,000
Landscaping / parks $4,000,000
Professional fees $1,100,000
Contingency $11,049,917
Total including contingency $121,548,650

Line items other than contingency sum to $110,498,733. The engineer narrative's pre-contingency figure of about $110,498,773 is close but not identical. A separate exhibit total of $119,776,493 is also preserved. The differences stay visible.

$121,548,650 estimate

Estimated

February 2024 master methodology materials include a project-cost estimate of $121,548,650 including contingency.

Official offering document As of Feb 1, 2024

Official document Sources (1) ↗

Source record

Evidence behind the record

Supports

February 2024 master methodology materials include a project-cost estimate of $121,548,650 including contingency.

  1. Master engineer's report and capital-improvement methodology, February 2024

    Document date
    Feb 1, 2024
    Source type
    Official offering document
    Confidence
    Primary source

About $110.5 million before contingency

Estimated

The same engineer material describes a pre-contingency capital-improvement total of approximately $110,498,773.

Official offering document As of Feb 1, 2024

Official document Sources (1) ↗

Source record

Evidence behind the record

Supports

The same engineer material describes a pre-contingency capital-improvement total of approximately $110,498,773.

  1. Master engineer's report and capital-improvement methodology, February 2024

    Document date
    Feb 1, 2024
    Source type
    Official offering document
    Confidence
    Primary source

$119,776,493 alternate exhibit

Estimated

A separate project-description exhibit showed a total of $119,776,493.

Conflicting sources As of Feb 1, 2024

Different lighting and contingency treatment. The tables are not collapsed into one total.

Conflicting sources Sources (1) ↗

Source record

Evidence behind the record

Supports

A separate project-description exhibit showed a total of $119,776,493. Different lighting and contingency treatment. The tables are not collapsed into one total.

  1. Master engineer's report and capital-improvement methodology, February 2024

    Document date
    Feb 1, 2024
    Source type
    Official offering document
    Confidence
    Primary source

Assessment Area One / Series 2025 estimate#

Estimated project cost, not a draw schedule
ImprovementEstimated cost
Wetland basins $500,000
Earthwork $2,400,000
Roadways $3,959,216
Entrance features $500,000
Water supply facilities — Described as privately funded and operated in the Series 2025 table. $7,094,807
Sanitary sewer facilities — Described as privately funded and operated in the Series 2025 table. $7,864,796
Stormwater management $1,141,490
Electrical $878,377
Landscaping / parks $750,000
Professional fees $1,000,000
Contingency $2,596,369
Total — A later allocation divides estimated benefit about $17,115,516.20 residential and $11,444,538.40 commercial. $28,560,055

The stated total is $28,560,055. The line items above add to $28,685,055. Both figures are shown. A later allocation of the stated total is about $17,115,516.20 residential and $11,444,538.40 commercial. Costs not funded by the Series 2025 bonds were expected to come from developer equity, deposits, and EB-5 loan proceeds.

More than $800 million claimed

Dated observation

A December 2025 government grant application claims more than $800 million in combined financing for the overall development. The filing does not break that figure down enough to treat it as cash already invested.

Public record As of Dec 10, 2025

Not treated as cash already invested.

Public record Sources (1) ↗

Source record

Evidence behind the record

Supports

A December 2025 government grant application claims more than $800 million in combined financing for the overall development. The filing does not break that figure down enough to treat it as cash already invested. Not treated as cash already invested.

  1. Florida Job Growth Grant proposal attributed to Okeechobee Utility Authority

    Document date
    Dec 10, 2025
    Source type
    Public record
    Confidence
    Primary source

    A combined-financing claim in this filing is not treated as cash already invested.

    Open original source ↗ Opens a leaving notice in a new tab.

Cite this page

Lakefront Okeechobee Report. “Project spending.” https://lakefrontokeechobee.com/financing/spending/

Keep the source dates and qualifications with any quoted figure. Download the public data.

The public record

Search Lakefront

Try 1464 Alfasi, block 6 lot 2, a parcel ID, or a topic.