OUA September 2025 packet: SR78 works and developer payment
OUA staff reported a developer cost-sharing payment and discussed the next SR78 water-main phase.
Site updated
Sources added through Nov 1, 2026; each fact retains its own date.
Glades County records checked through . Individual sources and historical collection batches retain their own dates.
← Findings and collection coverage · File catalog entry
What the document establishes#
OUA staff reported receipt of an initial $258,395.25 payment under the water-main cost-sharing agreement with Okeechobee Community Developers.
Document text PDF page44 ↗ Opens a leaving notice in a new tab.The Phase II notice to proceed was dated August 14, 2025, with B & B Site Development as contractor and scheduled substantial completion January 11, 2026.
Document text PDF page44 ↗ Opens a leaving notice in a new tab.The Phase III discussion concerned about 9,400 feet of additional piping. Preliminary estimates differed: approximately $2.8 million from Lakefront and $3.7 million from OUA staff, including contingency.
Document text PDF page43 ↗ Opens a leaving notice in a new tab.
Qualifications#
The completion dates are schedule targets. The packet’s requested RIF amount has an extra digit, so no precise grant amount is inferred from that line. The preliminary estimates are not money spent.
Page references count PDF pages from the beginning. Printed numbering may differ. These selected findings do not reproduce the entire document.
Related figures and claims#
Source record#
Public record Sources (1) ↗
Source record
Evidence behind the record
Supports
OUA staff reported a developer cost-sharing payment and discussed the next SR78 water-main phase.
-
OUA September 2025 packet: SR78 works and developer payment
- Document date
- Sep 16, 2025
- Source type
- Public record
- Confidence
- Primary source
- Location
- PDF pages 43, 44
The completion dates are schedule targets. The packet’s requested RIF amount has an extra digit, so no precise grant amount is inferred from that line. The preliminary estimates are not money spent.
Open the original document ↗ Opens a leaving notice in a new tab.
Cite this page
Lakefront Okeechobee Report. “OUA September 2025 packet: SR78 works and developer payment.” https://lakefrontokeechobee.com/expanded-records/expanded-b0df1800917461cb/
Keep the source dates and qualifications with any quoted figure. Download the public data.