DEP general permit: Phase 1A water-main extensions
DEP accepted general-permit coverage for Phase 1A water infrastructure.
Site updated
Sources added through Nov 1, 2026; each fact retains its own date.
Glades County records checked through . Individual sources and historical collection batches retain their own dates.
← Findings and collection coverage · File catalog entry
What the document establishes#
Permit 0081040-124 is issued April 8, 2025 and expires April 7, 2030. The listed works include 2,455 feet of 16-inch, 706 feet of 12-inch, 12,566 feet of 8-inch and 145 feet of 6-inch PVC, plus 22 fire hydrants and 35 sample points.
Document text PDF page1 ↗ Opens a leaving notice in a new tab.The permit requires departmental clearance before operation beyond testing and disinfection.
Document text PDF page2 ↗ Opens a leaving notice in a new tab.
Qualifications#
Compare the later partial clearances rather than treating the construction authorization as service clearance.
Page references count PDF pages from the beginning. Printed numbering may differ. These selected findings do not reproduce the entire document.
Timeline#
Source record#
Public record Sources (1) ↗
Source record
Evidence behind the record
Supports
DEP accepted general-permit coverage for Phase 1A water infrastructure.
-
DEP general permit: Phase 1A water-main extensions
- Document date
- Apr 8, 2025
- Source type
- Public record
- Confidence
- Primary source
- Location
- PDF pages 1, 2
Compare the later partial clearances rather than treating the construction authorization as service clearance.
Open the original document ↗ Opens a leaving notice in a new tab.